Water Treatment Plant 200 hl ph

Water treatment / softening with a capacity of 200 hlph constructed in 1991. The plant is still assembled and was in service until end of 2009. The plant is constructed as a twin plant. One water line was used for brew water and the other for service water, especially for the bottle washer.
Overview
Water Treatment
Softening
20 m³ph
200 hlph
1991 EUWA
2 x Ion Exchanger
- Acid cation exchanger
- Automatic indication for regeneration
With conductivity
- with blending
2 x 1050 l
…6,0 bar
20°C
1 x Lime water saturator
- with lime water vessel
930 l
…6,0 bar
20°C
2 x CO2-Sprinkler
- 1 x for brew water
- 1 x for brew water
-
1 x Hydrochloric Acid Vessel
- Double wall
- for regeneration
- with dosing unit
5 m³
…24 m³ph
30 °C
Pumps
Water meter
Flow meter
-
Space Requirement
- Twin plant with sprinkler
- Lime water saturator
- Hydrochloric Acid Vessel

~ 8,5 m x 2,1 m x 5,2 m high
~ 2,3 m x 2,0 m x 4,0 m high
~ 2,0 m x 2,0 m x 4,0 m high
Softener, as used
- Brew water line
- Service water line
- Layout

15,5° dH auf 4,0 °dH
15,5° dH auf 2,0 °dH
20°dH auf 0 °dH
With Switch Cabinet and Control 230/400V
7,5 kW